Steel

Meccon has constructed projects in all areas of steel making for thirty (30) years including blast furnaces, electric arc furnaces, coke batteries, coke by-product facilities, oxygen furnaces, hot and cold rolling mills and water treatment facilities. Meccon has constructed process and utility piping systems for the following:


New Thin Slab Caster Mini-Mill facilities:

  • Site Utilities (Including natural gas, water, sanitary and site fire protection loop)
  • Thin Slab Continuous Caster
  • Ladle Metallurgical Furnaces
  • Tunnel Furnace
  • Seven (7) Stand Hot Mill
  • Water Treatment Facilities (Including Contact, Non-Contact & Laminar Flow Cooling Water Systems)
  • Steel Coil Pickling

Integrated Steel Facility modifications and upgrading including:

  • Blast Furnace Relines
  • Coke Battery Upgrades
  • Coke Battery Emissions Desulfurization
  • Cold Mill Strip Pickle Line
  • Hot Strip Pickling Lines
  • Acid Regeneration Systems
  • Sheet Steel Electrogalvanizing
  • Waste Acid Containment Piping System
  • Coil Annealing Furnace Piping
  • Piping Systems Maintenance

Project Piping Installations exceeding 140,000 feet, including:

  • Cooling Water - 40,000 lin. ft
  • Hydraulics - 45,000 lin. ft
  • Lubrication Oils - 10,000 lin. ft
  • Natural Gas - 8,000 lin. ft
  • Compressed Air - 4,000 lin. ft
  • Lime Piping - 2,000 lin. ft
  • Argon - 2,000 lin. ft
  • Bldg Utilities - 29,000 lin. ft